Weighted duration% complete in P6

Anbin PonnithMember for 17 years 4 months
Created
1
3
0

Dear All,

 

How do I get weighted duration % complete in P6

 

Regards,

Anbin

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    your duration must be based

    your duration must be based something manhours cost whatever it may be 

    so if you have 100 manhours for an activity and you have 50 manhours remaining your weighted duration % complete is 50%