Dear Planners,

In P6, is it possible to know Who deleted the activity, and when deleted it. maybe the activity was deleted few days ago, several planners are working in one schedule.

 

Thanks for your reply.

 

BR

Jason

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    there are 3 levels of

    there are 3 levels of auditiing

    Level 0No Audit
    Level 1Row-level Audit. Audit only the operation without column details
    Level 2Column-level Audit without Blobs. Audit changes to the data at the column level but without Blob changes
    Level 3Full Audit. Audit changes to the data at the column level including Blob changes (Oracle only

    auditing_enable(<table_name>,<level>)

    auditing_disable(<table_name>)

    Examples for Oracle:

    Enable full auditing on all tables:  exec auditing_enable(null,3);

    Enable level one auditing on the task table:  exec auditing_enable('TASK',1);

    Disable auditing on PROJWBS: exec auditing_disable('PROJWBS');

    Disable auditing on completely:  exec auditing_disable(null);

    Example for SQL:

    Enable level 2 auditing on the ACCOUNT table:

    EXEC auditing_enable

        @ptable_name = N'account',

        @plevel = 2

     

    Use the settings_write_bool procedure to enable the overall auditing feature.

     

    Oracle

    exec settings_write_bool(1,'database.audit','Enabled');

    SQL Server

    exec settings_write_bool 1,'database.audit','Enabled';

     

    Example”

    database.audit.PROJWBS.Options=001: Row-level audit on deletes only.

    database.audit.TASKRSRC.Options=333: Fully audit.

  2. 0
    Nauman Reh ·

    Dear Zoltan,Please advise me

    Dear Zoltan,

    Please advise me on how to enadble auditing on Proimavera P6  tables (TASK) (TASKACTV) (TASKRSRC) (TASKFIN) (TRSRCFIN), so that all insert, update, delete are auditied in the (PRMAUDIT) table.

    I am using Oracle 10g express edition and ADMPRM$PM logins.

    exec auditing_enable(null,3); gives me error = ORA-00900: invalid SQL statement

    Please help

    Regards

    Nauman

  3. 0
    Zoltan Palffy ·

    try using call or Begin

    try using call or Begin instead of exec

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?