Require Activity % Complete equal to Expense % Complete

Irfan KhanMember for 17 years 3 months
Created
4
1
0

Hi to all experts,

 

I am using Primavera P6 R8.2

 

Here i am working with the schedule with 4,000 activities & almost 2,200 activities i have loaded Cost though Expenses.

The Problem i am facing that for example : one activity having 50% of  Activity % Completed so far, but when i am looking @ the Expenses Tab & its not showing me any actual cost for the same activity. Even i have tried to Import & Export throuhg excel in order to reflect the Activity% complete into Expenses % compete but due to (*) sign the values in exel sheet cant be modified.

 

Please anyone can help me in this regard.........i will be highly obliged  

 

4 replies

Oldest first
  1. 0
    Ahmed KHR ·

    Hi Irfan, Try to use global

    Hi Irfan,

     

    Try to use global change (Expense % = Activity %)

     

    Regards

  2. 0
    Irfan Khan ·

    i tried to resolve it through

    i tried to resolve it through Global Change......but unfortunately i didnt get way to fix it.... :(

  3. 0
    Zoltan Palffy ·

    no the global change

    no the global change suggestion will not work you can not cross % complete between activites and expenses even is you create a UDF

    I have supplied the solution here

    http://pmsite.com/forums/viewthread/3203

     

  4. 0
    Irfan Khan ·

    Thank you Mr.

    Thank you Mr. Zoltan.......... i got what i was looking for.