Require Activity % Complete equal to Expense % Complete
- Created
- 4
- 1
Hi to all experts,
I am using Primavera P6 R8.2
Here i am working with the schedule with 4,000 activities & almost 2,200 activities i have loaded Cost though Expenses.
The Problem i am facing that for example : one activity having 50% of Activity % Completed so far, but when i am looking @ the Expenses Tab & its not showing me any actual cost for the same activity. Even i have tried to Import & Export throuhg excel in order to reflect the Activity% complete into Expenses % compete but due to (*) sign the values in exel sheet cant be modified.
Please anyone can help me in this regard.........i will be highly obliged
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?