How To Assisgn Expenses in Primavera P6

Emily FosterMember for 15 years 2 months
Created
2
2
0

Here's a useful walk through on how to assign Expenses in Primavera P6 http://ow.ly/HOR2O

2 replies

Oldest first
  1. 0
    Kannan CP ·

    Hi Emily,If as per the

    Hi Emily,

    If as per the contract, only the BOQ amounts is allowed to be loaded in the programme, adding our internal expenses in the programme will increase the Total Budgeted Cost. This will not match with the Contract value and also can affect the Performance percentage complete.

    Is there any solution to address this?

    Thanks

    Kannan

  2. 0
    Sunil Babu ·

    Hi Kannan,Your question is

    Hi Kannan,

    Your question is interesting , I think we have options like Actual labour cost, Actual material cost, Actual total cost etc.

    Also You  have BL - Total cost (Excluding the indirect cost) . I think this will be enough for your EVA analysis.

    Any other options / comments will be highly appreciated.

    Best Regards

    Sunil.