Skip to content

Resource histogram by weeks.

Dennis HanksMember for 19 years 6 months
Created
6
2
0

I'm doing something wrong. I can't get my resource histogram to display by week. It sums to month. Help.

6 replies

Oldest first
  1. 0
    Tom Turnham ·

     

  2. 0
    Tom Turnham ·

    Are you just showing it at

    Are you just showing it at the buttom of the window using the 'Resource Usage Profile'?

    If so just right click in the right hand side of the window and select 'Timescale'. You can then chose the appropriate timescale (Month/Week)

    If you are copying it into Excel then go to the 'Assignments' window and do the same (right click in the right window and select 'Timescale')

     

    P.S a little courtesy goes a long way.

  3. 0
    Dennis Hanks ·

    Tom;Thanks for the response.

    Tom;

    Thanks for the response. Apparently the screen shot is not opening. I'll post again. It should show the timescale set at weeks for schedule and histogram, yet resources are grouped by month. I've sent a Service Request to Oracle - no response. Posting jpg now.

  4. 0
    Tom Turnham ·

    Strange. Im affraid I cant

    Strange. Im affraid I cant help.... When I change the timescale it amends the bars to suit

  5. 0
    Raymund de Laza ·

    Dennis,In User Prefrences..

    Dennis,

    In User Prefrences.. Resource Analysis.. Set Interval into weeks...

     

    Regards,

  6. 0
    Dennis Hanks ·

    Tom;The issue is ordinal

    Tom;

    The issue is ordinal dates. The workaround is a small pain - moving back and forth from Timescale Date Format changing in Primary Dates applying, changing again in Primary Dates and re-applying. Apparently the 'bug' has been around since P5. Not a high priority for Larry. Attached is what it should like. Thanks for trying.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?