Float bars on finished tasks
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 8 months
- Created
- 0
- 3
0
Hello planners,
can somebody please explain why Primavera P6 V7 or R8 displays a float bar when a task is completed, eventhough the Free float and Total float fields are empty?
these tasks are not out-of sequence
the float bar goes until the remaining start of the first successor in sequence
this happens for tasks wiche were critical or not critical all the same; how can it be possible to draw a float bar for a completed task?
thank you for your help and explanations
Alexandre
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?