Resource Price/Unit Changes & Baseline Values

Marc TimberlakeMember for 11 years 7 months
Created
1
4
0

Hi,

Hopefully someone here will be able to help.

I'm working on a project with a baseline that matches the approved client changes for reporting purposes. We are just about to apply new hourly rates to our labour resources (new rates from effective date). Will this automatically update the resources on the baseline? Ideally we want all values in the baseline to remain the same until such time that the uplifted rates are approved via change.

any help much appreciated.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    not it wil not update the

    not it wil not update the baseline the setting that were in effect when the resources were added remain ineffect. ALL of the rates in the baseline will rmain the SAME.

    If the baseline is assigned what you can do is select update baseline and check

    Update Existing activites already in the baseline

    then check When updating resource assignments data, include:

    and then check Update existing resources and role assignments 

    and then check Budgeted Units and cost 

Log in or join to reply