Zero Duration % complete

Paul ZachariaMember for 12 years 3 months
Created
5
1
0

Hii,

I get 0 duration % complete for one particular set of activity codes at the WBS level, but all other activities which are in progress/ completed rolls up to some value in the WBS level.

The activity type assiged is Fixed Durations & Units for all activities.

Please advice.

Paul

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Your Original duration and

    Your Original duration and your remaing durations are equal causing the % complete to be equal.

    Hence Performance % = Activity % Complete = Duration % Complete =  (OD - RD) /OD = 0%

    to fix this run a global change 

    where

    planned start = start
    planned finish = finish

    this will allow the WBS summary activity to calculate a correct Percent complete value 

  2. 0
    Paul Zacharia ·

    I ran the Global change. But

    I ran the Global change. But then the other WBSs which were showing some value for Duration % complete also increased to a non realistic value (66%), where most of the activities are not yet started / completed. 

    The program is not resource and cost loaded and hence i cant get the performance % complete.

    Could you please suggest any other solution. 

    Thanks,

    Paul.

     

     

     

  3. 0
    Zoltan Palffy ·

    if you are using physical %

    if you are using physical % complete you can run a global change 

    where

    duration % Complete equal physical % complete

  4. 0
    Paul Zacharia ·

    I am using Duration %

    I am using Duration % complete. 

  5. 0
    Zoltan Palffy ·

    I am not sure what you are

    I am not sure what you are trying to summarize in terms of % complete but some things can not be summarized by % complete becasue you can use 3 different types of % complete. Duration % Complete, physical % complete and unit % complete by tring to do this would be like mixing apples, oranges and pears.

    The summary band for either Schedule % complete or Performance % complete will always be calculated as 

    (BCWS  * 100) /BAC so it would be Budgeted Cost for Work Scheduled times 100 divided by Budget at Completion