Resource Leveling

Moutaz AldeibMember for 22 years 9 months
Created
3
2
0

Dear Planners,

How to make Primavera does not revert the original schedule when re-schedule the program after resource leveling is done.

Best,

Moutaz

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    in the leveling option make

    in the leveling option make sure that automatically level resources each time you schedule a project is unchecked

    also under the scheduel calculations F9 Options make sure that Level Resources during schedueling in NOT checked

    Scheduling the project (without leveling it) will remove any changes to dates that were made by leveling the project.

  2. 0
    Moutaz Aldeib ·

    Thanks Zoltan, but it is the

    Thanks Zoltan, but it is the opposite you check "automatically level resource each time you schedule project" in order not to revert to the original schedule.

    Best,

  3. 0
    Zoltan Palffy ·

    you are correct sorry I mis

    you are correct sorry I mis read your post. I thought that you wanted it to revert back. I think you have the answer now anyway. That is where the setting is either way.