Skip to content

Calendar changed not effect to Original Duration and Lag duration

Sony LeiMember for 15 years 10 months
Created
2
2
0

Dear all, Could any one help me how to change activities Calendar from Old Caledar to new Calendar without effect to Original Duration and Lag duration. I have followed below instruction but still cannot keep the Original Duration and Lag Duration as the same when applied old Calendar. https://www.youtube.com/watch?v=Wd8z70Cx6zU thanks

2 replies

Oldest first
  1. 0
    Sony Lei ·

    I want to focus on Lag

    I want to focus on Lag duration, because it will follow predecessor activities Calendar, and when predecessor activities change Calendar, it will change also, i dont know how to keep it as original Lag duration...

  2. 0
    Zoltan Palffy ·

    go to enterprise calendars

    go to enterprise 

    calendars and create a new calendar

    now go to activities add a column for calendar (its under general)

    click in the calendar column change the first one in that column to the new calendar that you just added.

    now hold the shift key and click on the last activity and make sure all activirtes are highlighted 

    right click and select fill down

    press f9 and rescheduel the project

    go to the projects directory and make sure that your project is highlighted

    click on the defaults tab and on the right select the new calendar that you just added 

    now when you add a new activity it will ue the newly created calendar.

    the duration of the lag does not change unless YOU change it. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?