Hi All,
I am in the process of resources/budgeted units export to excel, modify it and import back to P6.
While during the export of budgted unit value to excel- you might have noticed a green colour small icon in each cell at the top left corner. Is it possible to remove quickly without doing one by one, since there are thousands of activities. It is not possible to do the auto sum of the cells because of this icon.
Please share, if there is an easy idea
Thanks
Best Regards
Kannan