Resetting the Baseline in a Project with Progress Applied?

Kt G23Member for 11 years 3 months
Created
5
2
0

Hi I was just wondering if anyone cold provide any guidnace on resetting the baseline in P6 when your project already has progress in it? For example, I have a project that has progress applied for 6 months and now have a Compensation Event (Delay Claim) which needs to be added to baseline. Does anyone have a step by step process that I should go through to reset the baseline please? I know that if I apply the Current Baseline it will pick up the new activities for the Compensation Event in the future but what should I be doing with the Completed activities? When resetting the baseline should Actual Start & Finish Dates for Completed activities be the new Planned Start & Finish dates of new baseline?! Any advice anyone could give would be greatly appreciated. Many Thanks

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    if you do not have a baseline

    if you do not have a baseline you will have to copy the current schedule and then destatus the schedule to get an unprogressed schedule ot use as your baseline.

    if you want a step by step process see my post at the link below.

     

     http://pmsite.com/forums/viewthread/3064/

     

  2. 0
    Kt G23 ·

     

  3. 0
    Kt G23 ·

    Brilliant many thanks for

    Brilliant many thanks for that Zoltan!

    My schedule isn't actually resource or costs loaded but that information is very useful for the future.

    I do actually have an original baseline so that's not an issue. I guess my real question is when resetting the baseline (due to agreed change in scope) on a project that already has progress in it, should the new baseline show;

    1. the original baseline dates prior to the data date

    OR

    2. the actual start & finish dates of progress that has occurred prior to the data date

    Thanks

  4. 0
    Zoltan Palffy ·

    use the actual start & finish

    use the actual start & finish dates of progress that has occurred prior to the data date

    this is your NEW line in the sand this is your new measuring stick 

  5. 0
    Kt G23 ·

    Excellent thank you :-)

    Excellent thank you :-)