Resetting the Baseline in a Project with Progress Applied?
- Created
- 5
- 2
Hi I was just wondering if anyone cold provide any guidnace on resetting the baseline in P6 when your project already has progress in it? For example, I have a project that has progress applied for 6 months and now have a Compensation Event (Delay Claim) which needs to be added to baseline. Does anyone have a step by step process that I should go through to reset the baseline please? I know that if I apply the Current Baseline it will pick up the new activities for the Compensation Event in the future but what should I be doing with the Completed activities? When resetting the baseline should Actual Start & Finish Dates for Completed activities be the new Planned Start & Finish dates of new baseline?! Any advice anyone could give would be greatly appreciated. Many Thanks
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?