Budgeted Cost Calculation
- Created
- 6
- 3
Hi,
I am stuck with an issue related to the budgeted cost calculation, where the normal procedure is (Budgeted Units x Price/Unit= Budgeted Cost).
My setting for unit of time is hour and the price/unit is 1. The problem is in the calculation process of BC, which always consider a value of 0.125 to multiply with the BU in order to get the BC.
For eg: BU=100 and price/unit=1, but the BC is calculated as 100x0.125 =12.5
If the setting for unit of time is changed to day, the calulation will be 100x1 =100, which I think is wrong.
All other resources are working perfectly except one (with above issue).
Am I missing any setting for this resource?
Thanks and Regards
Kannan
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?