Same Resources for different Projects

Riyas AhmedMember for 11 years 2 months
Created
4
3
0

Hi everyone....Is it a good practice to use the same resources in multiple projects?? If it's okay, then wouldn't the parameters(eg: Resource Calendars,Unit Rates etc.) assigned to resources in a previous project change when i modify the parameters of resources for a new project?

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    The real question is why

    The real question is why would you want to use a global resource ?

    Well if your goal is to measure resources globally or company wide and want to know how a resource is being planned and actualized then a global resource could be used. However if your resource tend to be more project spedific then it would be better to use a project spefific resource where variables can be input 

  2. 0
    Rafael Davila ·

    Sharing resources among jobs

    Sharing resources among jobs is the order of the day on work by Utilities such as Water and Electrical. It is common to assign the same crew several jobs.  It is not unusual for a job to have assigned several such crews. It is called portfolio/enterprise project management and goes further than managing regular resources, it is frequently limited/driven by financial resources availability.

    Zoltan has a point, it is not always good idea to move resources between jobs.  There is not a simple answer to your question.

  3. 0
    Riyas Ahmed ·

    Thank you Zoltan and

    Thank you Zoltan and Rafael...

  4. 0
    Zoltan Palffy ·

    if you were looking to level

    if you were looking to level the same resources across ALL of your porjects then a typical same resource would be the way to go.