Help Required - How to actualise several activities at once

Thomas NicholsonMember for 20 years
Created
3
3
0

Morning all,

I wonder if somenoe can tell me a quick way to actualise several activities at once in P6?

I am working on a programme that has several structures within it each with their own WBS section, however a couple of the structures have been removed from our workbank until more funding comes along. So not wanting to remove them entirely I want to actualise all activities in those WBS sections only at the date we were told to defer the work.

Any ideas please?

Thanks

Thom

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you have 3 optionsoptions #1

    you have 3 options

    options #1 (use a global change)

    Tools Global Change 

    where wbs equals (whatever it is) 

    then actual start = select {Custom} then select the date that you want to use

    and actual finish = select {Custom} then select the date that you want to use

    then select change on the right 

     

    option #2 (use fill down)

    filter for the activities that you want 

    add the actual start and finish columns

    click in the actual start column for the 1st activity and put the date in

    select the rest of the activities and right click and select fill down

    click in the actual finish column for the 1st activity and put the date in

     

    option #3 (export to excel and import to P6)

    export the activities that you want to excel 

    make sure to include the actual start and finish columns and in the export filter for the activities that you want

    populate the actual start and finish dates in excel 

    save the file

    import the file back into p6

     

  2. 0
    Thomas Nicholson ·

    Zoltan,As usual you a mine of

    Zoltan,

    As usual you a mine of information.  The actual Start/Finish columns did the trick.  Option 1 is too scary with our system, I've lost far too much data to Global change and Option 3 our security settings do not allow importing of anything.   Option 2 did the trick though.

     

    Thanks for the assistance, greatly appreciated.

     

    Thom

  3. 0
    Zoltan Palffy ·

    there are always several ways

    there are always several ways to do things in P6.

    if you haven't already 

    I would add a note to the notebook field for each activity where you did this and note that the structures were put on hold until funding becomes available. 

    I might also add a code and tag each of these activities with a unique code something like "ON HOLD"

    This will give you the ability to easily find them in the future or not to show them at all.

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?