Updating Problem

Yahya AderemiMember for 11 years 2 months
Created
4
2
0

Dear all, I want to be updating percentage comple so I rename the "Performance %Complete Colum" as , but when I try to enter a value, it only display 6%, no matter the value it will display 6%.

Please help solve this problem

Thanks

4 replies

Oldest first
  1. 0
    Ahmed Aziz ·

    Dear yahya,if you want to

    Dear yahya,

    if you want to update the percantage complete, you need to know the % complete type for each activity and update accordingly.

    here is a better method: show the activity % complete column and update it

  2. 0
    Zoltan Palffy ·

    this is not the proper way to

    this is not the proper way to update a schedule

    if you are going to use performance % complete then you need to change the % complete type physical

    and you need to indicate an actual start date for the activity and then the performance % complete

    if the activity is complete you need to indicate the actual finish date  

  3. 0
    Yahya Aderemi ·

    @Ahmed Aziz, thanks for your

    @Ahmed Aziz, thanks for your reponse.

    What you stated is exactly what I did but my problem is anytime I input a value for %complete in the colum, it only dislay 6% alone. e.g, if I type 50% complete for activity, the colum will display 6%. If I enter 20%, it will still display 6%. I don't know why

  4. 0
    Zoltan Palffy ·

    renamainig a column doe snot

    renamainig a column doe snot effect the functionality of that field

    try using duration % comeplete and update that 

    also what is the duration TYPE set to  ?

    and what is the activity type set to ?