HOW TO EXPORT PRIMAVERA .XER ILE INCLUDING ALL MAINTAINED BASELINES???

Ali MurtazaMember for 11 years 2 months
Created
4
3
0

Dear Professionals,

Is there any way to export xer file including all maintained baselines?

Regards

Ali

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    upgrade to version 15

    upgrade to version 15

  2. 0
    Ali Murtaza ·

    Dear Zoltan Palffy,Thanks, i

    Dear Zoltan Palffy,

    Thanks, i will definitely upgrade to R.15

    Ali

  3. 0
    Alexandre Faulx-Briole ·

    Ali,until you upgrade to P6

    Ali,

    until you upgrade to P6 R15, you can easlly export baselines:

    1. Restore existing baselines (Project, Maintain baselines, Restore): P6 will create a new project from the baseline

    2. Export the current project and the restored baseline from Database 1

    3. Import the current project and the baseline to Database 2

    4. Create the project baseline in the Database 2 by Project, Maintain baselines, Add, the use the option #2

    Be aware that P6 R15 no longer allows to update a baseline; as far as I am concerned, this is a considerable downgrade in the software features, and I will reinstall a previous release (8.3 or 7) of the software

    Alexandre

  4. 0
    Zoltan Palffy ·

    yes Alexandre you can do that

    yes Alexandre you can do that but that was NOT the question

Log in or join to reply