S-Curves in Primavera P6 Professional

Emily FosterMember for 15 years 2 months
Created
6
2
0

We're frequently asked if Primavera P6 Professional is capable of displaying S-Curves. Sure, it can do that. You just have to know where to look. Here's a 'How To' on S-Curves in Primavera P6 Professional, how to configure them and how to print them http://ow.ly/RVmJT

6 replies

Oldest first
  1. 0
    Chris Rymer ·

    Project Tracker is an

    Project Tracker is an application that can create an S Curve directly from P6 without exporting to Excel. For more information on what the product can do or to get a free trial, go to http://www.willmer.co.uk
  2. 0
    Zoltan Palffy ·

    both p6 and project tracker

    both p6 and project tracker and create S curves 

    P6 can only do units and costs 

    project tracker can do units, costs, physical % complete and duration

    project tracker takes the info from the P6 xer file or the P6 database and generates the curves for you very easily 

  3. 0
    John Griffiths ·

    Take a look at Adrega PI

    Take a look at Adrega PI Reporting for Primavera. It's not just an S-Curve generator. Supports Gantt reporting, graphical and tabular information and period timephased reports. Imports "Period Performance" for all periods saved in a P6 project or you can save each period in Adrega PI. Its a "Cloud" solution and has a Dashboard which supports display of Gantts S-Curves and Tabular reports.

    Also supports Late schedule reporting as well as Resource S-Curves and multi project (program, portfolio) reporting.

    http://adrega.no/adrega-pi-solution/primavera-p6-dashboard-and-reporting/

  4. 0
    John Griffiths ·

    Take a look at Adrega PI

    Take a look at Adrega PI Reporting for Primavera. It's not just an S-Curve generator. Supports Gantt reporting, graphical and tabular information and period timephased reports. Imports "Period Performance" for all periods saved in a P6 project or you can save each period in Adrega PI. Its a "Cloud" solution and has a Dashboard which supports display of Gantts S-Curves and Tabular reports.

    Also supports Late schedule reporting as well as Resource S-Curves and multi project (program, portfolio) reporting.

    http://adrega.no/adrega-pi-solution/primavera-p6-dashboard-and-reporting/

  5. 0
    John Griffiths ·

    Take a look at Adrega PI

    Take a look at Adrega PI Reporting for Primavera. It's not just an S-Curve generator. Supports Gantt reporting, graphical and tabular information and period timephased reports. Imports "Period Performance" for all periods saved in a P6 project or you can save each period in Adrega PI. Its a "Cloud" solution and has a Dashboard which supports display of Gantts S-Curves and Tabular reports.

    Also supports Late schedule reporting as well as Resource S-Curves and multi project (program, portfolio) reporting.

    http://adrega.no/adrega-pi-solution/primavera-p6-dashboard-and-reporting/

  6. 0
    John Griffiths ·

    Take a look at Adrega PI

    Take a look at Adrega PI Reporting for Primavera. It's not just an S-Curve generator. Supports Gantt reporting, graphical and tabular information and period timephased reports. Imports "Period Performance" for all periods saved in a P6 project or you can save each period in Adrega PI. Its a "Cloud" solution and has a Dashboard which supports display of Gantts S-Curves and Tabular reports.

    Also supports Late schedule reporting as well as Resource S-Curves and multi project (program, portfolio) reporting.

    http://adrega.no/adrega-pi-solution/primavera-p6-dashboard-and-reporting/