Road Time Schedule

Moutaz AldeibMember for 22 years 9 months
Created
3
1
0

Dear Planners,

I will be in a new project for road design and construction which is new for me, can you provide me with the main activities for design and construction and how to link bewteen them (sequencing)?

Thanks in advance

Moutaz

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Preliminary Field Review

    Preliminary Field Review Report 

    Draft News Release

    Prepare for Public Involvement

    Distribute Survey Information and Request Design Input 

    Control Diagram

    Typical Sections

    Preliminary plan and profile sheets

    Preliminary cross sections 

    Establish Alignment & Grade

    Prepare Scope of Work Report 

    Approve Scope of Work 

    Prepare Plans for Plan-in-Hand 

    Plan-in-Hand Inspection

    Provide Construction Limits to R/W Agency 

    Design Miscellaneous Features 

    Final Plan Review 

    Final Plan Updates and Revisions

    Check Plans 

    Transmit to Contract Plans 

    Road Design Site Evaluation

    Design Conceptual Plan

    Final Mitigation Plan Development 

    Issue bids

    review bids

    award contract

    contractor create construction schedule 

     

  2. 0
    Moutaz Aldeib ·

    Thanks Zoltan,I mean the main

    Thanks Zoltan,

    I mean the main design and construction activities for road constructing.

    Best

  3. 0
    Zoltan Palffy ·

    DesignIssue Contract

    Design

    Issue Contract NTP

    Layout and Obtain Borings

    Prepare FDR

    Prepare Geotech Report

    Prepare DER

    Prepare 25% Highway Plans

    Submit 25% Design Package

    Review 25% Highway Package

    Review Geotech Report

    Schedule Design Public Hearing

    Conduct Public Hearing

    Respond to Comments

    Prepare 75% Highway Plans

    Submit 75% Design Package

    Review 75% Highway Plans

    Prepare 100% Highway Plans

    Submit 100% Design Package

    Review 100% Highway Plans

    Prepare PS&E

    Submit PS&E

    Review PS&E & Submit to CEPO

    Advertise

    Environmental Permitting

    Coordinate Early Environmental Documents

    Prepare ENF

    Review ENF

    Approve ENF

    Prepare CE

    Approve CE

    Prepare Sect. 106 Hist Arch

    Review Sect. 106 Hist Arch

    Approve Sect. 106

    Evaluate Programmatic 4(F) Applicability

    Draft Preliminary Programmatic 4(F)

    Review Programmatic 4(F)

    Approve Programmatic 4(F)

    Reqeust MESA Rare species survey

    Determine MESA Habitat

    Review and File MESA

    Approve MESA

    Delineate Wetland Resources

    Prepare ACOE PGP

    Review ACOE PGP

    Approve ACOE PGP

    Submit WQC

    Review and File WQC

    Approve WQC

    Prepare 25% HazMat Research

    Review 25% HazMat Research

    Review 75% HazMat Research

    Issue Environmental Clearance

    ROW

    Prepare Prelim ROW Plans

    Review and Accept Prelim ROW Plans

    Hold Town Meeting

    Perform Title Work

    Contact Property Owners

    Perform Appraisals

    Prepare Layout Taking Plans & Instrument (TPI)

    Review & Accept Layout TPI

    Approve Acquisition, Record and File

    Submit Community Compliance Package

    Review Community Compliance Package

    Issue Certificate