Copy & Paste WBS, error in activity IDs arrange
In the Open Standard
Mah FazelMember for 17 years
- Created
- 6
- 3
0
Hi all
I have a plan with WBS and some activities.
I Insert an activity between 2 activities and set its ID (for example in Tank1).
when I copy WBS and paste (for Tank2), the last inserted activity is created in end of created activities (in new ID sequence).all things ir right, only activity IDs are not as source.
Why and what must i do?
Thanks
I am using P6.0 (sql server)