Hi,

Today i have faced a strange problem with my P6, that the duration of my activities became zero, when i added resource and provided budgeted hours. Activity was fixed duration / units

Can someone help me to sort it out?

Regards,

Abilash 

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    filter for all activities add

    filter for all activities 

    add a column for duration type 

    change the first on to fixed duration/Units per time

    fill down for all of the duration types

    go to projects directory 

    make sure that your project is open and highlighted 

    go to the default tab

    under duaraiton type select 

    fixed duration/Units per time

     

    also check your activity type and make sure that it is task dependent NOT resource dependent 

  2. 0
    Abilash Palakkadan Mathew ·

    Zoltan,Thanks for your reply,

    Zoltan,

    Thanks for your reply, what you said is absolutely right that will work.

    But my problem is that i have to use fixed duration / units (not fixed duration / units per time).

    I have fixed the problem by re importing the OD. however for me it seems like a bug... but not sure. earlier this (OD) wasn't getting changed when i add resoruces with this type of activities.

    If anyone else got different opionion please share.

  3. 0
    Zoltan Palffy ·

    ok then here is why this is

    ok then here is why this is happening 

    Does the resource have 0 set for Default Units per Time ?

    AND

    Does the setting in the Projects View look under the Resource Tab is Drive activity dates by default selected ? 

    if so then this is the culprit

    to fix this 

    Go to the Projects directory check the Resource Tab and uncheck Drive activity dates by default

    and 

    go to the resource directory and select your resource and set the Default Units per Time in the Resource Dictionary under the Details Tab to something other than 0.

    because anything divided by zero is  ? 0