Skip to content

Material resource Default units/time

Pirzada Umair AhmedMember for 11 years
Created
1
3
0

Hi to all! I am a bit confused regarding default units/time for any resource matreial specially concrete.Somebody informed me that put ZERO in default units/time in any material resource and after doing this the budgeted units also become zero.Please suggest or guide me what is the correct thing in any Material resource case in P6.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    for material default

    for material default unit/time use 1 because any thing divided by zero or multiplied by zero is what  ? Yes zero

    so what it does is basically is multiplying the default units/time by the duration to get the budget amount and for distribution it is dividing this budget amount duration and is spreading this amount units/time by the start and end date of the activity. So multiplying and or divided anything by zero will be zero.

    for example if you have a resource for labor and set the default units/time to be 8 and you have a duration of 5 days it will take the 5 days time 8 hours per day 5*8=40 budgeted units. Then for the distribution it will spread the 40 hours by the units/time in this case 8 so it will show 8 hours per day for 5 day

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?