Actual units & EV did not update!!

X PlannerMember for 24 years 4 months
Created
7
17
0

Dear All, 

 

   After updating my program i found the earned value and the actual units for "some" activities equal to zero ( didnot update), 

so i had to fix it manually on excel and import on p6, i'm usining duration %.

Any idea what could be the reason? and how to fix?

Thanks.

7 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    use physical % complete

    use physical % complete

  2. 0
    Mehmet Akif İbrahimoğlu ·

    Hi, You can write your data

    Hi,

     

    You can write your data in UDF coulomn, after you import P6. And then Use Global change. 

  3. 0
    Zoltan Palffy ·

    to do what  ?

    to do what  ?

  4. 0
    X Planner ·

    Thanx Zoltan, I just wanted

    Thanx Zoltan, I just wanted to know why it doesn't show any values. (the explaination)

  5. 0
    Zoltan Palffy ·

    the reason is that you are

    the reason is that you are using duration % complete NOT physcial % complete

  6. 0
    X Planner ·

    Thanks Zoltan

    Thanks Zoltan

  7. 0
    Zoltan Palffy ·

    no problem

    no problem