Problem with resource after reinstalation. P6 'stand alone'
- Created
- 4
- 2
Good evening to All.
I work on "stand alone" version of P6. After reinstalation i have problems with resources.
I have created for my schedule labour resource with "default units per time" = 99/day. I have assigned it for few activities, put a number of budgeted units and I have started to schedule. It was ok. Everything was going just well. We were measuring progress of our project using this units.
...but...
After reinstalation of P6 when I opened my schedule, budgeted units for this activities were changed. The same with "default units per time" =9/d (?).
I don't have any idea what have happend. Maybe somebody had some similar problems with importing xer after reinstalation.
I will be grateful for any feedback.
taras83
4 replies
Oldest firstLog in or join to reply