Assigning task durations
- Created
- 3
- 2
Hello,
I am a beginner with Premavera. I work by exporting/importing Excel files.
I would like to assign my tasks a fixed/constrained duration. The purpose is to position these taks in my schedule only using this duration and one relationship (linking its start or end date respectively to the previous or following task).
Howerver, I have tried to put this duration in the "free_float_hr_cnt", "total_float_hr _cnt", "remain_drtn_hr_cnt" and/or "target_drtn_hr_cnt" fields, but everytime I reschedule (F9), the durations change...
For now, I have avoided the problem by creating two relationships for each task (for example one FS (lag = 0) and one FF (lag = task duration)), but this solution is not satifactory for me.
Does someone know how to do this ? As it seems quite simple, I assume that I simply did not find the right task field/property to configure.
Thanks in advance !
3 replies
Oldest firstLog in or join to reply