Assigning Resources to Project and WBS Level

Ken BarrettMember for 19 years 5 months
Created
10
5
0

I cant figure out how to assign resources to the project or WBS level for high level resource loading. Can anyone help me out?

 

Ken Barrett

10 replies

Oldest first
  1. 0
    Bong Yagahon ·

    What software are you using?

    What software are you using? If your using excel, i think nobody knows....

  2. 0
    Ken Barrett ·

    I am using P6

    I am using P6

  3. 0
    Bong Yagahon ·

    Ken, Im sorry but i dont know

    Ken, Im sorry but i dont know P6. Lets wait for the others to comment and help us out.

    Thanks.

    Pio

  4. 0
    Paul Harris ·

    KenThe client version of P6

    Ken

    The client version of P6 may only assign resources to activities.

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au- a Primavera scheduling software resources site

  5. 0
    Amasor Pius ·

    Good day all,Please can any

    Good day all,

    Please can any one with Primavera6 manual get in touch with me on piusamasor@yahoo.com

    I need it urgently, am presently using P3 and Project Professional.

  6. 0
    Dalida Rizk ·

    Dear all, do you know how we

    Dear all,

    do you know how we do a recurrent activity in Primavera P6?  I am not able to.  thank you.

  7. 0
    Mathieu ALBOUY ·

    Impossible, the only level

    Impossible, the only level you can assign resources is activity. To confirm that you can go to ressource assignment view, and you will figure out that the only assignment availbale is at activity level.

    But to resolve your issue you should know that you can assign resource to Macr/Master activity as LOE or WBS Summary. So if your WBS is well defined or if your network logic is good, this is for sure your only & best solution.

    Hope to answer,

    A+ les mecs

  8. 0
    Patrick Chuks ·

    PLease, I am very good with

    PLease, I am very good with P3, but have some challenges with P6 resource loading, I have two activityies with FS, assigned a workman(Carpenter 2 (in actual units of resource tab) for both activities, from the resource summary report, I was expectign to see a total required resource of 2 capenters since the activities are FS, but I am getting 4, please, what am I doing wrong, I urgently need your assistance as this will enable me know the right productivity.

     

    THank you

    My email is jemsenator(at)yahoo.com

  9. 0
    Mohd Syahrul ·

    It can't be done

    It can't be done
  10. 0
    Syed Abrar ·

    Hi, there are few simple

    Hi,

     there are few simple steps to laod resources for activities in P6.

    first step is u have to define resources if u don't have any. go to Enterprises >Resources >add

    u can add Labour / non labour / Material by choosing in Resource type column.

    then go to the activities. select particular activity & in activity form say add resource, pop comes up where u can select one r multiple resources. then u can specify how many per duration needed or budgeted resources per activity. by default it will linearly distributed for the assigned duration.pls see below

     

     

Log in or join to reply