Actual labor units in activity usage spreadsheet

Jean DesjardinsMember for 14 years 11 months
Created
2
3
0

Good Day P6 Users,

I have a project which started in March and I just completed October update.

I am copying units from activity usage spreadsheet to Excel to create a graph and I noticed that actual units distribution varies when I do some modifications on remaining activities without changing the data date.

I am wondering why are actual units changing even for march period ?

Does anyone have an explanation ?

Thank you.

Jean

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Jean,Suggestions:1. In

    Jean,

    Suggestions:

    1. In Resource detail, Uncheck the "Auto Compute Actuals"
    2. In Activity Details, Use a "Fixed Duration & Units" for Duration Type.

     

    Hope this will help.

  2. 0
    Rafael Davila ·

    http://primaveratips.blogspot

    http://primaveratips.blogspot.com/2012/12/financial-periods-and-project.html