Actual labor units in activity usage spreadsheet
In the Open Standard
Jean DesjardinsMember for 14 years 11 months
- Created
- 2
- 3
0
Good Day P6 Users,
I have a project which started in March and I just completed October update.
I am copying units from activity usage spreadsheet to Excel to create a graph and I noticed that actual units distribution varies when I do some modifications on remaining activities without changing the data date.
I am wondering why are actual units changing even for march period ?
Does anyone have an explanation ?
Thank you.
Jean
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?