Skip to content

BL1 Total Float Calculation Issues

Kyle ColcherMember for 11 years 4 months
Created
1
3
0

I am currently having issues with the value that is displayed in the BL1 Total Float column.

 

I can snap a baseline of the current project and this column will show a different value of than what the live project file shows.

 

For example :  Activity has float of -68 days in the current project (which is the  correct float).  I assign the current project as a a baseline and add the BL1 Total Float column.  This column displays -210 days of float.

 

Any ideas what may be causing this problem.  I do not think it is any logic issues because the open project is calculating the float correctly.  It is only to incorrect on the assigned baselines.

This is also true if I assign another project as a baseline.  If the project is opened alone, the correct float is displayed, once assigned as a baseline, the same issue happens.

Thanks,

 

Kyle Colcher

1 reply

Oldest first
  1. 0
    Neils Gao ·

    The dates used to show after

    The dates used to show after the baseline is saved is PLANNED START and PLANNED FINISH of the baseline schedule, so I am thinking the reason may be the planned dates are not exactly same with current dates in your current schedule, and the TF will be different as it calculated with planned dates I guess.

    The way to resolve it is to show planned start and planned finish column in the activity table and compare with current dates, copy to excel may be quicker I think. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?