Assigning resources from BL to update
In the Open Standard
Mohamed AbdalgawadMember for 14 years 11 months
- Created
- 4
- 1
0
Dear All
I finished base line
Then i made update, all this without assigning resources.
Then consultant asked me to assign resources, I did for the baseline.
now there is a way to make update again to resources BL , but because
I changed many relationships I want to know if there a way to move assignments from the BL to the update ?
Thanks in advance