Assigning resources from BL to update

Mohamed AbdalgawadMember for 14 years 11 months
Created
4
1
0

Dear All

I finished base line 

Then i made update, all this without assigning resources.

Then consultant asked me to assign resources, I did for the baseline.

now there is a way to make update again to resources BL , but because

I changed many relationships I want to know if there a way to move assignments from the BL to the update ?

Thanks in advance

 

4 replies

Oldest first
  1. 0
    Abilash Palakkadan Mathew ·

    Please do following

    Please do following steps Make a copy of baseline file Restore that baseline copy file Import the resource assigments into the restored file Assign this file back as the baseline By Abilash
  2. 0
    Abilash Palakkadan Mathew ·

    Please do following steps 1.

    Please do following steps 1. Make a copy of baseline file 2. Restore that baseline copy file 3. Import the resource assigments into the restored file 4. Assign this file back as the baseline By Abilash
  3. 0
    Mohamed Abdalgawad ·

    Thanks very much for response

    Thanks very much for response but may be i didn't make myself clear;

    I will ask anothe question:

    can i import relationships from update to BL ?

  4. 0
    Abilash Palakkadan Mathew ·

    The whole current schedule

    The whole current schedule can be updated to BL by update the baseline option. But I prefer not to do that. If i was there at your situation i will set the current file as a new baseline and assign this new BL to current schedule to monitor furthed. If required i will be available on 00971563911927