Skip to content

Assigning resources from BL to update

Mohamed AbdalgawadMember for 14 years 11 months
Created
0
3
0

Dear All

I finished base line 

Then i made update, all this without assigning resources.

Then consultant asked me to assign resources, I did for the baseline.

now there is a way to make update again to resources BL , but because

I changed many relationships I want to know if there a way to move assignments from the BL to the update ?

Thanks in advance

 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?