Subcontractors as resource
- Created
- 4
- 2
Please help...
So I went ahead and set up all of my activities with dates, predecessors, successors etc for a project which is a construction contract where I have some of the work that is self performed, some where I have vendors providing materials, and subcontractors who have provided me their quotes. Next, I set up all of the vendors and subcontractors as resources. I would like to know if there is a way to load the costs (quotes) from each subcontractor into the activities they each perform.
For example:
Subcontractor A - Quote Amount: $900,000
Activity A - 12 days
Activity B - 12 days
Activity C - 26 days
Activity A should be only 20 percent of the total quote.
Activity B 25%.
Activity C 55% of the total dollar value.
I am stuck at how to proceed. Please help...
Thank you,
Eddie
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?

