Primavera P6 wandering Baselines
- Created
- 4
- 24
Hello, I was just wondering if anyone could help me. I am working on a number of programmes / schedules within Primavera P6. All of which have baselines. I have set the Project and Primary baselines within 'Assign Baselines', but every now and then when I return to the programme to run a filter or print, the baselines have re set back to >Current Schedule> for the Primary baseline or selected an alternative / old baseline for the project baseline. Has anyone any idea why it does this or if there is something I am missing / doing wrong. It doesn't do it every time I access the programme, sometimes it is as I left it.
Many thanks
4 replies
Oldest firstLog in or join to reply