Assigning resources to activities based on multiple perameters
- Created
- 0
- 3
We have multiple activities (tests) which need to be planned using a number of test properties (vehicles) to maximise utilisation and shorten total test time.
The vehicles are allocated against the tests based on a number of perameters. - Currently this is done (badly) in peoples heads.
eg Test A requires V8 engine and AWD
Test B requires any engine RWD
Test C requires any engine and AWD
Vehicle 1 is a V8 RWD, Vehicle 2 is a V6 AWD.
Test A and C can use Vehicle 2, Test B can use vehicle 1
We are just starting to use P6 and I wondered if I can use it to automatically allocate the tests (activities) against the available test properties (resources) based on the resource properties.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?