Replace projects

Hadi DzaieMember for 10 years 9 months
Created
2
2
0

Dear All,

I have a 2 projects and I want to dissolve one of them into the other (i.e) I dont want to delete one and rename the other one to take over , I want to copy one project and past it into the other project. how can this happen?

2 replies

Oldest first
  1. 0
    Jerome Odeh ·

    Hadi,The solutions in the

    Hadi,

    The solutions in the post below should help you. Best to always search the forum before posting new questions.

     

    http://www.planningplanet.com/forums/primavera-version-pm5-pm6/499514/how-do-you-mergre-2-different-projects-one-project

     

    =jerome
    http://plannerstips.blogspot.co.uk/

  2. 0
    Zoltan Palffy ·

    one way to do it is to open

    one way to do it is to open one project and have the other project as an xer file. Select file import and during the importing under the IMPORT ACTION change this option and select 

    ADD INTO EXISTING PROJECT instead of the default setting create a new project 

Log in or join to reply