Remaining Late Cost earlier than data date

Justin MehaffeyMember for 10 years 9 months
Created
1
2
0

My issues is that my remaining late cost is showing up earlier than my data date. I've gone through and removed all my Finish Constraints and the Must Finish By date so there is no negative float in my schedule. Scheduled the project and it still shows this way. I haven't gone through and done a full analysis but I can see there are some of these issues on LOE activities. I think i recall at one point there was a bug in P6 that this issue showed up on LOE, not sure if it's been resolved. I'm trying to find a work around but have exhausted every option I can think of. Are there any suggestions or work arounds to get the remaining late to calculate correctly? Thanks!

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    if you are cost loading LOEs

    if you are cost loading LOEs you have to assign a curve to them or the cost will show up on the first day that the activity starts.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?