How to group and sort for a single resource ID into multiple criteria in resources usage profile

Galav DaniMember for 12 years 2 months
Created
1
4
0

Hello experts...

Imagine there is a resource defined as “Fitter” and I had allocated that resource in many activities in schedule. 

Now my schedule comprises of different units called as unit A, B, C Etc… 

Now during resource usage profile how can I show unit wise amount of over allocation of “Fitter” ?

What method should i use?

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Hi...Set a Max Unit / time

    Hi...Set a Max Unit / time for the Resource.

Log in or join to reply