Activity % Complete

Diane JonesMember for 10 years 10 months
Created
3
1
0

Hi,

Can anyone advise why I can't change the 'Activity % Complete'??? I have % Complete Type as 'Physical' and need to update a programme.

I'm new to this and I'm sure it's something simple, help most appreciated.

Thanks,

Diane

3 replies

Oldest first
  1. 0
    Leighton Rogers ·

    Hi Diane Im realitivity new

    Hi Diane

     

    Im realitivity new to this as well

    Have you started the activity? and checked the activity box to started in the status bar? then update the physical % complete

     

    regards

     

    leighton

  2. 0
    Zoltan Palffy ·

    in the % compleyte type you

    in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level. 

    the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete. 

  3. 0
    Zoltan Palffy ·

    in the % compleyte type you

    in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level. 

    the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete. 