Primavera P6- Hide the completed activities in a schedule

Zabiulla ShakirMember for 10 years 8 months
Created
3
2
0

Hi !

How do i hide the completed activities in a schedule? 

Thanks..

3 replies

Oldest first
  1. 0
    Jerome Odeh ·

    Go to Views >> FiltersUnder

    Go to Views >> Filters

    Under Show activities that match checkbox, tick Any selected filter

    Then select the default filters "In Progress" & "Not Started"

    Click Apply & OK. Your completed activities should be hidden from your layout.

  2. 0
    Zabiulla Shakir ·

    Thank You!! :)

    Thank You!! :)

  3. 0
    Zoltan Palffy ·

    or filter where activity

    or filter where activity status is not equal to complete

Log in or join to reply