Resource Limitation/Restriction in Primavera
- Created
- 7
- 1
7 replies
Oldest first- 0IKIrfan Khan ·
Hi to all Experts, I was
Hi to all Experts,
I was wondering that how to manage my limited resources through Primavera P6.
If the Case is like that :
I have 6 activities
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship.
the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.
hence, i want restriction on activities with the help of due to limited resource.
Hope i everything is clear here, for more information please see the snap shot.
thanks...... :)
- 0IKIrfan Khan ·
Hi to all Experts, I was
Hi to all Experts,
I was wondering that how to manage my limited resources through Primavera P6.
If the Case is like that :
I have 6 activities
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship.
the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.
hence, i want restriction on activities with the help of due to limited resource.
Hope i everything is clear here, for more information please see the snap shot.
thanks...... :)
- 0IKIrfan Khan ·
Thaks Mr. Raymund for your
Thaks Mr. Raymund for your reply,
Settting MAX Unit/Time is not solving my problem, let me explain you again that :
I have only one crew which is working parellay with 1st group of activities i.e. activity A, B & C, second part is that my activties D, E & F will start just completion of activity A, B & C.
all activities has assigned one crew only which will work only when my Group 1 Activities will finish, therefore i am wondering an option whcihc will stop me to start any activity in group to unless all of actvities finish in Group 1.
Hope you understand what i am looking for.
thanks.....
- 0ZPZoltan Palffy ·
this depends on your logic
this depends on your logic if Activity A, B & C have Start to Start relationship with one crew and Activity D, E & F have Start to Start relationship with the same crew thne make activity D a successor to activity A and make E a successor to activity B and make activity F a successor to activity C or make D a successor to activity A all with FS relationships.