Skip to content

Resource Limitation/Restriction in Primavera

Irfan KhanMember for 17 years 3 months
Created
7
1

7 replies

Oldest first
  1. 0
    Irfan Khan ·

    Hi to all Experts, I was

    Hi to all Experts,

     

    I was wondering that how to manage my limited resources through Primavera P6.

     

    If the Case is like that :

     

    I have 6 activities 

    Activity A

    Activity B

    Activity C

    Activity D

    Activity E

    Activity F

    Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship. 

    the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.

    hence, i want restriction on activities with the help of due to limited resource.

    Hope i everything is clear here, for more information please see the snap shot.

    thanks...... :)

     

     

     

     

  2. 0
    Irfan Khan ·

    Hi to all Experts, I was

    Hi to all Experts,

     

    I was wondering that how to manage my limited resources through Primavera P6.

     

    If the Case is like that :

     

    I have 6 activities 

    Activity A

    Activity B

    Activity C

    Activity D

    Activity E

    Activity F

    Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship. 

    the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.

    hence, i want restriction on activities with the help of due to limited resource.

    Hope i everything is clear here, for more information please see the snap shot.

    thanks...... :)

     

     

     

     

  3. 0
    Raymund de Laza ·

    Set the MAX Unit/Time for the

    Set the MAX Unit/Time for the Crew in the resource Pane. In your example the MAX unit is 3 Multiplied by Working Time for the crew per day. Say your crew will work 8hrs per day then your MAX will be 24hrs/day.

    Hope this will help

  4. 0
    Irfan Khan ·

    Thaks Mr. Raymund for your

    Thaks Mr. Raymund for your reply,

     

    Settting MAX Unit/Time is not solving my problem, let me explain you again that :

    I have only one crew which is working parellay with 1st group of activities i.e. activity A, B & C, second part is that my activties D, E & F will start just completion of activity A, B & C. 

     

    all activities has assigned one crew only which will work only when my Group 1 Activities will finish, therefore i am wondering an option whcihc will stop me to start any activity in group to unless all of actvities finish in Group 1.

     

    Hope you understand what i am looking for.

     

    thanks.....

  5. 0
    Raymund de Laza ·

    After Setting my

    After Setting my suggestions... run Resource Levelling with priorities.

    Hope this will help.

  6. 0
    Wang Chao ·

    Actually it is the workflow

    Actually it is the workflow function, I think this is can't automatic generate (depending on the current reviosn function) .It only can be found by manual.

  7. 0
    Zoltan Palffy ·

    this depends on your logic

    this depends on your logic if Activity A, B & C have Start to Start relationship with one crew and Activity D, E & F have Start to Start relationship with the same crew thne make activity D a successor to activity A and make E a successor to activity B and make activity F a successor to activity C or make D a successor to activity A all with FS relationships.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?