Skip to content

PROBLEM WITH LEVEL 1 ROLL UP

Rasheed AjirotutuMember for 12 years 5 months
Created
5
2
0

Dear Colleague,

Please i have a problem with my programme with 550days duration on level 1 Roll up. After 8months of update i notice that the roll up duration on the level 1 is reduced by 7days now(543days) . I got confused because the same calender is in use since day 1 the update started 8 months ago

Please i need help from my noble colleague how to resolve this issue.

5 replies

Oldest first
  1. 0
    Ronald Weaver ·

    I believe the summary bar

    I believe the summary bar duration is calculted using the Default Calendar. I would start there.

  2. 0
    Rasheed Ajirotutu ·

    Thanks you Ronald but the

    Thanks you Ronald but the same default Calender was in use from the begining of the update.

    Do you have any other reason i may consider for this change.

    Hoping to hear from you soon

  3. 0
    Raymund de Laza ·

    The default Calendar shall be

    The default Calendar shall be the same Calendar assigned to all Acyivities.

  4. 0
    Jerome Odeh ·

    Rasheed,Is your Finish Date

    Rasheed,

    Is your Finish Date the same date as it was 8 months ago? 

    =jerome

  5. 0
    Zoltan Palffy ·

    2 thngs you are either 7 days

    2 thngs you are either 7 days ahead of schedule or any new activities were added using a different calendar.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?