Skip to content

Total float of 800

Vigeeth SalianMember for 10 years 7 months
Created
4
1
0

Hi,

I am getting total float of 800 and above, which is a mistake.

 

Plz help me resolve it.

Mail me to Vigeethsalian@gmail.com, i will send my programm so that you can take a look.

 

thanks & Regards,

Vigeeth

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,you should check the

    Hello,

    you should check the "Must finish by" field in the "Project Details" form, "Dates" tab

  2. 0
    Zoltan Palffy ·

    1. make sure that EVERY

    1. make sure that EVERY activity has a predecessor and a successor

    2. if you are using ANY constraint dates make sure that YEAR is correct and its not a typo

    3. go to project directory make sure your project is highlighted and select the dates tab and make sure that under the Must Finish By Date that you list your project completion date there.

    4. Press F9 review results

  3. 0
    Nguyen Hung ·

    It seems that some

    It seems that some predecessors and successors are missing or wrong constraint date.

  4. 0
    Zoltan Palffy ·

    Alex I already mentioned that

    Alex I already mentioned that it is my item #3

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?