Resource usage profile

Kannan CPMember for 18 years 5 months
Created
3
16
0

Hi all,

I have few activities in the program with similar resource, but in different time period.

When i tried the resource usage profile, it shows the units/cost distribution for the overall time period.

Is it possible to see the unit/cost distribution for only one activity, in the profile?.

 

Thanks

Kannan

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    yes just filter for that

    yes just filter for that activiity 

  2. 0
    Kannan CP ·

    Hi Zoltan,i found it

    Hi Zoltan,

    i found it already...

     

    Thanks for the reply.

  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help