Changing the Version Number of a Primavera P6 XER File

Emily FosterMember for 15 years 2 months
Created
2
1
0

I know this may be a bit of old news, but it still keeps coming up. Here's how to change the version number of a Primavera P6 XER file if you're having trouble importing it http://ow.ly/ZQSfI

I hope this helps!

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Emily the information in link

    Emily 

    the information in link is correct they way that you have it but there is an exception.

    In P6 15.2.3, Primavera has added a checksum to the XER and XML files to “identify whether the XML/XER has been modified externally”. So if you change it the check sum feature makes the file unusable. 

    However, in P6 15.2.5, they have removed the checksum because it created more issues than it resolved

  2. 0
    Emily Foster ·

    Thnaks Zoltan - I've updated

    Thnaks Zoltan - I've updated it to reflect your comments. I didn't know that so it's very helpful. Thanks!