WBS disappeared from the programme

M SagarMember for 11 years 9 months
Created
1
5
0

Hi guys,

I am facing a weird problem with WBS on a specific programme. When I am grouping the activities by WBS under the Group & Sort option its not getting grouped so. Plus, under the WBS view its noy showing any dates and activities against each WBS. Actually, there are many activities under each WBS and there are various level of those WBSs as well. Please help!

Thanks!

Normal programme's WBS view

The problematic programme's WBS view

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    Try to summarize the project

    Try to summarize the project again but from what I see it looks like activities have not been assigned to a wbs

    go to tools then summarize

Log in or join to reply