Skip to content

Problem with importing update to the baseline.

Ahmed SamirMember for 10 years 7 months
Created
2
3
0

hey there,

i face a problem while i'm importing update to the baseline, the progress percentage for all activities wasn't the same in site so i changed all Performance % Complete, Start date and Finish date for all activities, there were some activities in the site completed and in the Xer file is still have % or with Zero %...and some activties percentages got increased and some got decreased...

when i prepared the Excel sheet and import it to baseline to re-update everything from the begining, the baseline didn't change and everything still Zero.
 

anyone have a solution for this problem ??

 

Regards, 

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    make sure that your duraiton

    make sure that your duraiton type is fixed duration & units/time

    run a global change 

    where performance % complete is not equal to 0

    then

    duration % complete equals performance % complete

    and importing for progress MUST have start TIMES for activities with actual starts and must have start and fnish TIMES for activities with actual starts and finishes

  2. 0
    Muhammad Bilal ·

    All Members Good Day. I am

    All Members Good Day.
    I am facing one problem which is i made Rev-05 of my In-Progress Project in which i added one Activity given Relationships to some other activities. I made the Rev-05 by Restoring the Baseline. Now when i assigned this Latest Baseline to Updated Progressed Schedule, the added new Activity is not shown. Please let me help out. How can i Show effectively the added activity in the new baseline with Actual Progress Schedule.
    Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?