Negative float and project end dates
In the Open Standard
Karim SolimanMember for 10 years 6 months
- Created
- 3
- 2
0
Hello,
On a schedule for a construction project I have created a LOE activity called 'monthly meetings'. This activity has its own caldendar with only 2 working days every month.
I have a start milestone for 'construction start' and a finish milestone for 'construction end'. To set up the LOE activity correctly, should I add the Construction Start as a predecessor with SS relationship and Construction end as successor with FF relationship?
I tried this and it gives me negative float.....!
Thanks
Karim
3 replies