Skip to content

Global Change Not Working

Adam MullMember for 10 years 6 months
Created
1
2
0

Here is the situation.  I am trying to take an in progress schedule and use it for a new project.  The unstatused baseline is not available, only an in-progress version.  Normally this is no problem, I simply run a global change for activity status not equal to not started then equal not started and reset remaining durations to original durations.

 

However, this time it is not working.  It is throwing an error on about 100 activities saying it cannot set them to Not Started because of actuals.  There are no resources in this schedule.  I have checked several times.  

 

Does anyone know what is up?  I can change this manual by clicking off the finish date, changing remaining to original manually and then clicking off the start date but that is a tedious manual process.  Plus I just want to know why in a several thousand activity schedule, the global change would work for 90% of the activities but not 100 or so activities.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    this is a 2 step process. 1.

    this is a 2 step process.

    1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units to Original

    2. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.

    3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule.
     
    To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.
     
    4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
     
    5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down
     
    global change #1
    Subject Area: Activity Resource Assignments
    Where: 
    Resource Type equals Material
    Then:  Actual Material Units = 0
     
    2nd Global change 
    Subject Area: Activities
    Where: Activity Status  is not equal to   Not Started
    Then: Activity Status equal Not Started
     
    3 global change 
    Add durtions  to activities by running global change for not started activits
    Subject Area: Activities
    Where: Activity Status is equal to Not Started
    Then: Reaming duration = Original duration

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?