Cost of level of effort activity

Shafak SalamMember for 10 years 5 months
Created
3
1
0

I have a level of effort activity with duration % complete. Cost is assigned to it as material resources price. But the cost is not getting distributed through the duration of the activity. In the profile/spreadsheet, the cost just stays in the start date of the activity. No idea why..

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    go to the activity directory

    go to the activity directory then the resource tab right click in the bottom resource window add a column for curve

    then assign a curve to the resource

  2. 0
    Shafak Salam ·

    Thank you..

    Thank you..

  3. 0
    Shafak Salam ·

    Thank you..

    Thank you..