Skip to content

Resource Assignment Original Duration

Wadi El-Din HammoudaMember for 12 years 3 months
Created
0
2
0

Hi,

I applied a filter on the Activities pane then went on the Resource Assignment pane, applied the same filter and came up with the same start and finish dates on the summary, but different Original Duration.

My question is, what are the possible reasons for that?! And is there a solution to show the same Original Duration?!

Regards,

Wadi El-Din Hammouda 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?