Adding New Activity in restored Baseline then Assigning it into Progressed Schedule

Muhammad BilalMember for 11 years 6 months
Created
1
2
0
All Members Good Day.
 
I am facing one problem which is i made Rev-05 of my In-Progress Project in which i added one Activity given Relationships to some other activities. I made the Rev-05 by Restoring the Baseline. Now when i assigned this Latest Baseline to Updated Progressed Schedule, the added new Activity is not shown. Please let me help out. How can i Show effectively the added activity in the new baseline with Actual Progress Schedule.
 
Thanks

1 reply

Oldest first
  1. 0
    Arun Balakrishnan ·

    I also face the same

    I also face the same probelm,

    I solve the issue by adding the same activity, link and same activity ID  in Actual progress Schedule.