Adding New Activity in restored Baseline then Assigning it into Progressed Schedule
In the Open Standard
Muhammad BilalMember for 11 years 6 months
- Created
- 1
- 2
0
All Members Good Day.
I am facing one problem which is i made Rev-05 of my In-Progress Project in which i added one Activity given Relationships to some other activities. I made the Rev-05 by Restoring the Baseline. Now when i assigned this Latest Baseline to Updated Progressed Schedule, the added new Activity is not shown. Please let me help out. How can i Show effectively the added activity in the new baseline with Actual Progress Schedule.
Thanks
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?